Knowledge Base

Contract End Date must not be later than Base Job End Date

Contract End Date is Banner's term for Encumbrance End Date.  The Encumbrance Date entries only appear on Faculty ePAFs.  Verify these two items:

1) You have chosen the wrong ePAF, not a Faculty ePAf for a faculty title.  You must delete this ePAF and restart with a Faculty ePAF.

2)  Look in the Approval Type "Encumbrance 9 Month".  When you are ending a job, the Encumbrance End date must not occur after the Job End Date.

 

Tip:  Remember that Banner uses 'Contract' to reference encumbrance dates on Faculty ePAFs.

Attached Files
There are no attachments for this article.
Comments
There are no comments for this article. Be the first to post a comment.
Name
Email
MENU